PMI · PMI-SP
Credential from the Project Management Institute for project schedulers. The exam has 170 multiple-choice questions in 210 minutes and covers schedule strategy, planning and development, monitoring and controlling, closeout and stakeholder communications.
Practice Questions
838
≈ 4 practice exams
Duration
210 minutes
Passing Score
Not published
Difficulty
ProfessionalLast Updated
Oct 2026
The PMI Scheduling Professional (PMI-SP) is a Project Management Institute credential for people who build and maintain project schedules. PMI still lists it as an active certification. The exam has 170 multiple-choice questions and a 210-minute time limit, and PMI publishes it in English only. Results are reported as pass or fail, and PMI does not publish a numeric passing score.
PMI's published exam content outline splits the PMI-SP into five domains: Schedule Strategy (14%), Schedule Planning and Development (31%), Schedule Monitoring and Controlling (35%), Schedule Closeout (6%) and Stakeholder Communications Management (14%). Topics include work breakdown structures, activity sequencing, critical path and critical chain, resource-constrained schedules, schedule risk analysis such as Monte Carlo simulation, baselines, change control and earned value reporting. The outline PDF PMI hosts carries a 2012 copyright date.
This page offers 838 PMI-SP practice questions, 30 of them free, written around those five domains. Use them to check how well you can apply scheduling techniques to short scenarios. They are independent study material and are not affiliated with PMI. For exam rules, fees and eligibility, rely on PMI's certification page and the PMI Certification Handbook, because those details can change.
The PMI Scheduling Professional (PMI-SP) certifies the skills used to develop, maintain and analyze project schedules. PMI lists 170 multiple-choice questions, a 210-minute time limit and English as the exam language. PMI's certification page and the June 2026 PMI Certification Handbook both still include the credential.
PMI positions the PMI-SP for people with roughly 2-3 years of experience who specialize in project scheduling, such as project schedulers and planners, and who meet one of PMI's three eligibility sets.
Set A: secondary degree, 40 months of project scheduling experience within the last 5 years and 40 hours of scheduling education. Set B: four-year degree, 24 months of experience within the last 5 years and 30 hours of education. Set C: GAC-accredited bachelor's or postgraduate degree (or global equivalent), at least 12 months of scheduling experience within the last five consecutive years and 30 contact hours of formal scheduling education. PMI accepts hours spent in training for Microsoft Project and other scheduling tools toward the education requirement.
170 multiple-choice questions in 210 minutes, English only. PMI handbook: once the application is approved you have a 1-year eligibility period with up to three attempts, and fees are paid again for attempts two and three. Results are pass or fail with no published numeric passing score.
The PMI-SP is a PMI credential in project scheduling. PMI states it demonstrates the ability to develop and maintain project schedules and manage timelines across global teams. Holders maintain it with 30 PDUs per 3-year cycle.
Answer 5 sample questions and see the explanation for each one. The full bank has 838 questions, enough for 4 full-length practice exams.
Try it, no sign-up1. A PMI-SP identifies that Activity P has Total Float of 8 days and Free Float of 3 days. What is the Interfering Float for Activity P? (Select one!)
Explanation
Interfering Float equals Total Float minus Free Float. Interfering Float = 8 - 3 = 5 days. This represents the portion of total float that, if consumed, will delay the Early Start of one or more successor activities but not the project completion date. The relationship is always: Total Float ≥ Free Float ≥ Independent Float. The 5 days of interfering float indicates that delaying Activity P by more than 3 days (its free float) will impact successor activities' early starts.
2. Using the same three-point estimates from the previous activity (O=8, M=12, P=22), what is the standard deviation for this activity? (Select one!)
Explanation
Standard deviation is calculated using the formula: σ = (P - O) / 6. Calculation: (22 - 8) / 6 = 14 / 6 = 2.33 days. Standard deviation measures the uncertainty or variability in the duration estimate, with higher values indicating greater uncertainty. This value is used in schedule risk analysis and Monte Carlo simulations. The 4.67 option incorrectly divides by 3 instead of 6. The 7.00 option uses only half the formula. The 14.00 option fails to divide the range by 6.
3. A PMI-SP calculates Interfering Float for Activity K, which has Total Float of 12 days and Free Float of 5 days. What is the Interfering Float? (Select one!)
Explanation
Interfering Float equals Total Float minus Free Float. For Activity K: Interfering Float = 12 - 5 = 7 days. This represents the portion of total float that, if consumed, will delay successor activities but not the project completion date. The 5 days of Free Float can be used without affecting any successors, while the additional 7 days of Interfering Float will impact successor Early Start dates but still keep the project on schedule. The relationship Total Float ≥ Free Float ≥ Independent Float always holds true.
4. A manufacturing project has calculated critical path duration of 180 days, but the customer contract requires completion in 165 days. What is the Project Float? (Select one!)
Explanation
Project Float is calculated as Required Completion Date minus Calculated Critical Path Duration. Project Float = 165 - 180 = -15 days. Negative float indicates the project schedule cannot meet the required deadline and is already behind before work begins. This requires schedule compression through crashing or fast-tracking. Positive 15 days reverses the calculation incorrectly. Zero days would only occur if required date matched calculated duration. The 180-day option confuses project float with critical path duration.
5. A PMI-SP analyzes a project network where Activity M has ES=15, EF=22, LS=18, LF=25. Activity M has one successor Activity N with ES=22. What is the Free Float for Activity M? (Select one!)
Explanation
Free Float is calculated as ES(successor) minus EF(current activity). For Activity M, Free Float = 22 - 22 = 0 days. This means Activity M cannot be delayed without affecting the Early Start of its successor Activity N. The Total Float for Activity M is 3 days (LS - ES = 18 - 15), but this delay would consume float from the successor chain. The 7-day option incorrectly uses duration. The 10-day option has no mathematical basis in the given values.
Yes. PMI's PMI-SP certification page is live and lists the exam, and the PMI Certification Handbook revised June 2026 still includes it in the certification program. We found no retirement notice for it on pmi.org.
PMI lists 170 multiple-choice questions and 210 minutes. The exam is available in English.
PMI does not publish a numeric passing score for the PMI-SP. Its handbook says passing scores for PMI exams are set by psychometric analysis, and results are reported as pass or fail.
PMI offers three sets. Set A is a secondary degree, 40 months of project scheduling experience within the last 5 years and 40 hours of scheduling education. Set B is a four-year degree, 24 months of experience within the last 5 years and 30 hours of education. Set C is a GAC-accredited bachelor's or master's degree (or global equivalent), 12 months of scheduling experience within the last five consecutive years and 30 contact hours of scheduling education.
After approval you have a 1-year eligibility period and can take the exam up to three times in it, paying fees again for the second and third attempts. After three failed attempts you must wait 1 year from your last exam before reapplying.
PMI-SP holders must earn 30 professional development units (PDUs) in each 3-year cycle. PMI counts a PDU as one hour spent on activities such as learning, teaching, presenting, reading, volunteering or creating content.
PMI Risk Management Professional (PMI-RMP)
PMI-RMP · 826 questions
Project Management Professional (PMP)
PMP · 613 questions
PMI Professional in Business Analysis (PMI-PBA)
PMI-PBA · 846 questions
PMI Agile Certified Practitioner (PMI-ACP)
PMI-ACP · 843 questions
Project Professional Advanced (PPA)
PPA · 834 questions
Certified Associate in Project Management (CAPM)
CAPM · 626 questions
$29.99
One-time access to this exam