PMI · PgMP
Validates experience and judgment in leading related projects as a coordinated program across strategic alignment, the program life cycle, benefits, stakeholders, and governance.
Practice Questions
847
≈ 4 practice exams
Duration
240 minutes
Passing Score
Pass/Fail
Difficulty
ProfessionalLast Updated
Oct 2026
PgMP evaluates leaders who coordinate related projects as one strategic effort, and the assessment begins before exam day. Applicants must document qualifying experience and pass a peer panel review before scheduling the exam. Program Life Cycle Management dominates the formal blueprint at 44%, followed by Stakeholder Engagement at 16%.
The current exam contains 170 multiple-choice questions and allows 240 minutes. It is offered in English and Chinese (Simplified) at Pearson VUE centers or, where permitted, through online proctoring. PMP can satisfy the project-management component of an eligibility pathway, but it does not replace the required program-management experience.
This 847-question PgMP practice bank supports repeated judgment calls across strategy, the program life cycle, benefits, stakeholders, and governance. Start with 30 free questions, then keep asking what protects the program's combined strategic outcome rather than what merely optimizes one component project.
Program Management Professional (PgMP) is built for program leaders who coordinate related projects as one strategic effort, and its assessment starts before exam day. Applicants must document qualifying project and program leadership, then pass a peer panel review before they can schedule the exam.
The current exam has 170 multiple-choice questions and allows 240 minutes. Program Life Cycle Management carries 44% of PMI's formal March 2024 Exam Content Outline, making it the dominant study area.
PgMP is for experienced practitioners responsible for multiple related projects whose combined outcomes support organizational strategy. Its scope covers strategic alignment, life-cycle leadership, benefits, stakeholders, and governance across complex programs.
PMP can satisfy the project-management component of an eligibility pathway, but it is not a universal prerequisite. Applicants still need the program-management experience required for their education route and must pass the PgMP panel review.
With a secondary diploma, PMI requires 48 months of project-management experience or PMP plus 84 months of program-management experience. With a bachelor's degree or higher, it requires 48 months or PMP plus 48 months of program-management experience. With a bachelor's degree or higher from a GAC-accredited program, it requires 36 months or PMP plus 36 months.
Qualifying experience must fall within the past 15 years. After payment, PgMP-certified volunteer program managers evaluate the experience summaries in the application; candidates must pass this panel review before scheduling the exam.
The PgMP exam has 170 multiple-choice questions and a 240-minute appointment. It is available in English and Chinese (Simplified) through Pearson VUE testing centers or, where permitted, online proctoring. PMI does not currently publish a PgMP-specific scored/unscored split or a fixed numerical passing score.
The current U.S. page lists $800 for PMI members and $1,000 at full price. Approved candidates receive a one-year eligibility period and may attempt the exam up to three times, paying again for subsequent attempts.
PgMP demonstrates that a practitioner has passed both an experience-based peer panel review and PMI's program-management examination. It is relevant to roles responsible for coordinating related projects, aligning them with strategy, and sustaining benefits across organizational boundaries.
To maintain PgMP, holders need 60 PDUs per three-year cycle: at least 35 Education PDUs, no more than 25 Giving Back PDUs, and at least eight Education PDUs in each PMI Talent Triangle area.
5 sample questions with answers and explanations. The full bank has 847 questions, enough for 4 full-length practice exams.
Preview — answers shown1. Your program's Cost Performance Index (CPI) is 0.87 and Schedule Performance Index (SPI) is 0.92. The Budget at Completion (BAC) is $3,600,000 and current Actual Cost (AC) is $1,800,000. Calculate the Estimate at Completion (EAC) assuming performance continues at current efficiency. (Select one!)
Explanation
EAC equals BAC divided by CPI when assuming current cost performance continues. EAC equals $3,600,000 divided by 0.87, which equals $4,137,931. This calculation projects total program cost based on current efficiency. The calculation of $3,132,000 incorrectly multiplies BAC by CPI instead of dividing. The calculation of $3,912,000 uses an incorrect formula. The calculation of $5,400,000 appears to use a different incorrect approach, possibly involving the schedule variance.
2. During benefits analysis and planning, you quantify a benefit as reducing customer complaint resolution time from 72 hours to 24 hours. However, this improvement does not directly reduce operational costs or increase revenue. How should this benefit be classified? (Select one!)
Explanation
Tangible and non-cashable is correct because the benefit can be directly measured with specific metrics (72 hours to 24 hours) making it tangible, but it does not directly convert to financial savings making it non-cashable. Tangible benefits have quantifiable metrics. Cashable benefits directly save money or increase revenue. This benefit improves service levels and customer satisfaction without immediate cash impact. Intangible benefits cannot be directly measured, such as improved morale or brand reputation. This distinction is critical in Benefits Management domain for setting appropriate measurement criteria and stakeholder expectations.
3. Your enterprise transformation program has a Budget at Completion (BAC) of $4,200,000. Current performance metrics show: Earned Value (EV) = $1,800,000, Actual Cost (AC) = $2,100,000. The governance board requests a forecast of total program cost assuming current cost performance trends continue. What is the Estimate at Completion (EAC)? (Select one!)
Explanation
The Estimate at Completion (EAC) when assuming current cost performance continues is calculated using the formula EAC equals BAC divided by CPI. First, calculate the Cost Performance Index: CPI equals EV divided by AC equals 1,800,000 divided by 2,100,000 equals 0.857. Then calculate EAC: EAC equals 4,200,000 divided by 0.857 equals approximately 4,900,000. The CPI of 0.857 indicates the program is experiencing cost overruns, spending approximately $1.17 for every dollar of planned value delivered. If this performance trend continues, the program will require approximately $4,900,000 to complete all work, representing a $700,000 overrun from the original budget. This forecast provides the steering committee with critical information for funding decisions and corrective action planning.
4. During program execution, you are conducting earned value analysis. Aggregated data from all component projects shows: Budget at Completion equals 12 million USD, Earned Value equals 5.2 million USD, Actual Cost equals 5.8 million USD, and Planned Value equals 6 million USD. What is the To-Complete Performance Index assuming the current Cost Performance Index continues? (Select one!)
Explanation
TCPI with current CPI continuing is calculated as TCPI equals the quantity Budget at Completion minus Earned Value divided by the quantity Budget at Completion minus Actual Cost. CPI equals Earned Value divided by Actual Cost equals 5.2 million divided by 5.8 million equals 0.897. TCPI equals 12 million minus 5.2 million divided by 12 million minus 5.8 million equals 6.8 million divided by 6.2 million equals 1.097, approximately 1.15 when rounded. This indicates the program must perform at 1.15 efficiency for remaining work to complete within budget, requiring 15 percent better performance than current efficiency. The calculation shows the program is currently over budget with CPI below 1.0 and requires improved performance to avoid further overruns.
5. You are developing Key Performance Indicators for program benefits measurement. The business case identifies a strategic benefit of improved market responsiveness enabling faster product launches. What type of KPI structure should you establish? (Select one!)
Explanation
Outcome KPIs measure the results achieved from program outputs and are appropriate for measuring market responsiveness improvements. Time from concept to launch directly measures the improved capability that delivers strategic value. Output KPIs measure deliverables created, not the improved responsiveness capability. Activity and input KPIs measure effort and resources invested but not results achieved. The distinction between outputs, outcomes, and benefits is critical in program management where outcomes represent changed capabilities that enable benefit realization.
No. PMP can satisfy the project-management portion of the experience requirement, but it is not a universal prerequisite. You must still meet the applicable program-management experience requirement.
A secondary diploma requires 48 months of project experience or PMP plus 84 months of program experience; a bachelor’s route requires 48 plus 48 months; and a GAC-accredited degree route requires 36 plus 36 months.
After payment, PgMP-certified volunteer program managers evaluate the experience summaries in your application. You must pass this peer review before PMI lets you schedule the exam.
The exam has 170 multiple-choice questions and a 240-minute appointment. It is available in English and Chinese (Simplified) at Pearson VUE centers or, where permitted, online.
Program Life Cycle Management is 44%, Stakeholder Engagement 16%, Strategic Program Alignment 15%, Governance 14%, and Benefits Alignment 11%.
You may attempt the exam three times during the one-year eligibility period. To maintain PgMP, earn 60 PDUs every three years, including at least 35 Education PDUs and at least eight in each Talent Triangle area.
PMI Construction Professional (PMI-CP)
PMI-CP · 840 questions
PMI Professional in Business Analysis (PMI-PBA)
PMI-PBA · 846 questions
Portfolio Management Professional (PfMP)
PfMP · 845 questions
PMI Project Management Office Certified Professional (PMI-PMOCP)
PMI-PMOCP · 847 questions
Project Management Professional (PMP)
PMP · 613 questions
Project Professional Advanced (PPA)
PPA · 834 questions
$17.99
One-time access to this exam